Data centres and cloud

Turning existing data-centre assets into a regional cloud business

What we look at when an organisation wants to grow existing data-centre assets into a regional data-centre and cloud player.

Many organisations in the Gulf already own data-centre capacity: built for their own IT, for a group of companies or as part of a real-estate portfolio. With demand rising, the question is whether those assets can become a commercial data-centre and cloud business. In early 2025 we built such a strategy for an organisation with exactly that ambition. The approach applies well beyond that one case.

Demand is real, and power is the constraint

Demand for AI-ready capacity offers opportunities across the value chain. McKinsey's data-centre demand model suggested that global demand for data-centre capacity could more than triple by 2030. Turner & Townsend expected the Middle East market to roughly double over the same period, driven by the digital economy and AI applications.

Saudi Arabia and the UAE lead the region. The UAE's high data consumption and early use of AI put it at the front of the GCC's data-centre plans. At the time, its active projects amounted to about USD 1.2 billion, with a further pipeline of about USD 433 million. Turner & Townsend's 2023 cost index also showed consistent year-on-year construction cost inflation across all regional markets.

The catch is power. As more data centres are built and each needs more of it, power supply is becoming a constraint even in markets that have traditionally attracted clusters of data centres. A strategy that starts from existing sites has an advantage here, but only if the available power and the path to more of it are known.

Decide which services to sell

A modern data centre sells far more than floor space. The service catalogue typically spans:

Each step up the stack brings higher margins and a different organisation, skills base and risk profile. The strategy has to say which services are offered locally, regionally and globally, and which sites deliver them.

Plan for the technology shifts

New capacity should be planned for technologies that change cost and density, not just for today's design. We screened ten potentially disruptive technologies against five goals: lower energy consumption, better efficiency and planning, faster deployment, more agile IT and network workloads, and higher resilience. They include direct liquid cooling, chiller-free cooling, data-centre micro-grids, software-defined power, micro-modular embedded data centres, silicon photonics, storage-class memory, open-source infrastructure, data-centre management as a service and distributed workload resilience.

Design resilience from the customer's requirement

Availability decisions must follow the business-continuity and disaster-recovery requirements of the systems' owners, not the other way round. Three site patterns cover most needs:

PatternProtects againstTrade-off
One core site, two fire-containment zonesLocal incidents such as fireNo protection if the whole site or area is lost
Dual core with a remote disaster-recovery siteLocal and regional incidents such as a power outageThe DR site, well over 30 km away, runs asynchronously, so a small amount of data can be lost
Twin core in close proximity, plus remote DRSite failure, with databases running active-activeSynchronous paths need sites close together; the remote DR site adds cost

Choose the tier level per workload

Tier levels drive redundancy, failover design and cost. Network and IT owners must decide which systems belong in which tier.

TierAvailabilityExpected unplanned downtimeTypical user
I99.671%28.8 hours a yearSmall, cash-based business with low dependence on ICT
II99.741%22.7 hours a yearSome online revenue; can tolerate scheduled downtime
III99.982%1.6 hours a yearGlobal presence, most revenue online, high cost of downtime
IV99.995%0.4 hours a yearBusiness model entirely dependent on IT, extremely high cost of downtime

Building everything to Tier IV is rarely economical. Matching tiers to workloads is where much of the capital efficiency comes from.

From analysis to a build plan

The work runs in two phases, each closed by a steering-committee decision:

  1. Analyse: an as-is review of sites, services, processes, organisation and infrastructure topology; site design (categories and regions); service design (local, regional, global); a service catalogue; and a business case per level. It ends with approval of the site concept and the investment.
  2. Design: the regional data-centre design and common standards, the technical design of shared services such as directory, DNS and WAN, roles and support processes, a gap analysis per site and a regional investment plan. It ends with budget approval, transition preparation and the data-centre build plan.

The lesson

Existing assets are a head start, not a strategy. They become a regional data-centre and cloud business when the service catalogue, the resilience design and the tier choices follow real customer requirements, and when power and investment are planned site by site.

Market data reflects public sources as of January 2025: McKinsey's data-centre demand model and Turner & Townsend's Data Centre Cost Index 2023. Tier availability figures follow the commonly used tier classification. Figures have not been updated since. Client details are confidential.